Installation of a Submerged Turret Production Buoy

Posted by: Global Maritime | Date: September 20, 2016

Client: Ocean Installer

Timeline: 2015 - 2016

Global Maritime's Aberdeen office worked alongside our partners at Vryhof Anchors to deliver a time sensitive installation of a Submerged Turret Production Buoy for Ocean Installer.

The buoy was transported to the field, lifted into the water and connected to the moorings in the Aje Field offshore Lagos, Nigeria.

GM was involved in multiple levels of the design, operations and safety considerations throughout the installation.

Our technical expertise in previous projects was a valuable resource as the project was done in only 8 weeks and would normally be done in 6-8 months.

Interested in more news and updates from Global Maritime?